Performed Projects
- Renovation of division unit (Phase 1)
- Renovation of precise instruments of FURFURAL units I & II
- Creation of central unit along with new DCS control system
- Creation of power plant (installation of 4 gas generators)
- Renovation of systems and facilities of power distributions
- Installation of R.O. system in order to refine the system tank water
- Installation of new assembly line of barrel production and barrel coloring
- Installation of new boiler (Inauguration 2008)
- Creation of industrial and sanitatary sewage filteration-refinement system (Inauguration 2008)
- Creation of condensate recovery system
- Expansion of official building
- Installation of double ignition furnace of FURFURAL unit
- Creation of cooling tower of division unit
- Creation of new recreational facilities and dining salon
- Renovation of the water network for fire fighting
- Installation of camera system and refinery security system
- Development of lighting system of refinement building
- The new building of work site